Project
Metal Roof-Over on an Occupied Industrial Unit
Brief
An aging cement-sheet roof was covered with a new insulated steel roof on a spacer system, avoiding the cost and disruption of stripping the old roof while the business kept working below.
Solution
The problem
The owner of an industrial unit needed a long-term answer to an aging cement-sheet roof that had reached the end of its service life. Stripping the roof and replacing it was outside the budget, and the business needed to keep operating throughout the work.
Why a roof-over
TCR proposed a roof-over, also called overcladding: a new metal roof built on top of the existing one. The old sheets stay in place, sealed beneath the new roof, so there is no strip-out, no open roof over the business and far less waste. The aims were to:
- extend the life of the roof without removing it;
- add insulation and improve weather protection;
- keep the cost within the budget;
- work around tight access and a building in daily use.
The system
New profiled steel roof sheets were installed over the existing roof on a spacer system. Support rails carry the new roof at a set height above the old one, and the space between holds new insulation. New flashings were made for the ridge, edges and other details. The sheeting, fasteners, support rails, flashings and insulation were selected to work together as one system, giving a watertight, low-maintenance roof with better insulation values than the old one.
See roof overlays and roof-overs for when a new roof can be built over an existing one.
Tight access and a working building
A narrow side road ran along the building, limiting where scaffolding could stand and how materials could be delivered. TCR worked with the scaffolding contractor on an access design that fit the space. The business stayed open throughout, so the work was phased to keep disruption to its daily operations low, with strict safety controls on site.
Schedule and outcome
The roof-over took six weeks. The photographs show the roof before the work, with its weathered sheets, and the finished building.
- Delivered on time and within the budget.
- The old roof is sealed beneath the new one, with no strip-out.
- Better insulation and weather protection.
- Minimal disruption to the business below.