Project
TPO Roof Replacement on Occupied Office Buildings
Brief
How TCR plans a TPO roof replacement above occupied offices: moisture survey, sections made watertight every day, odor and noise control, HVAC coordination and closeout.
Solution
Start with what is under the membrane
Before a replacement is designed, the existing roof is surveyed. Core cuts show which layers are there, and a moisture survey finds wet insulation. That decides whether the roof must come off down to the deck or whether a recover over the existing roof is allowed, how much insulation the new roof needs to meet the energy code, and where tapered insulation and crickets are needed to stop water from ponding.
Watertight at the end of every day
On an occupied building, no section of roof is left open overnight. The roof is replaced in sections sized to what the crew can strip, insulate and cover in one day, and each section is sealed to the old roof with a temporary tie-in before the crew leaves. The weather forecast decides each morning how much is opened.
Odor, noise and the people below
Adhesives and primers give off odors that can be drawn into the building through rooftop air intakes. Attachment methods that use less adhesive, such as mechanically fastened or induction-welded membranes, cut odors at the source, and intakes near the work are protected or shut down by agreement with the building engineer. Noisy work, such as tear-off and fastening above meeting rooms and other sensitive areas, can be scheduled early, late or on weekends.
Rooftop equipment
HVAC units, exhaust fans and antennas are worked around in coordination with the building’s mechanical contractor. Units on curbs that are too low for the new roof height have their curbs raised, and every disconnection and restart is planned so the offices below keep their heating and cooling.
See TPO roofing and flat roof waterproofing.
Edges, drains and closeout
Roof edges are finished with edge metal tested for wind uplift, and drains, scuppers and overflows are reset to suit the new roof level. Before closeout, the seams are probed and every detail is inspected, and the owner receives the roof plan, product data and maintenance guidance. Where a manufacturer’s warranty is part of the specification, the manufacturer’s own inspection is arranged before the roof is handed over.